QUESTION 1 OF 25
A completes a task in 24 days and B in 36. They work together for 6 days, then B leaves. How many additional days does A need?
- A.13 days
- B.14 days
- C.15 days
- D.12 days
- E.16 days
Show correct answer & explanation
Correct answer: B — 14 days
Combined first-phase work is(d/2)(1/(2d)+1/(3d))=5/12. The remaining 7/12 takes A 2d×7/12=7d/6 days.