Leaderboard
Time, work and wages · All sets

Main Examination · Quantitative Aptitude

Time, work and wages · Practice Set 02

25 questions. Read answers without starting an attempt, or practise with feedback or a timer.

QUESTION 1 OF 25

A machine makes a batch in 16 hours. A second machine is 25% more efficient. Both operate together. What is their combined completion time? Round your answer to two decimal places.

  1. A.5.11 hours
  2. B.6.11 hours
  3. C.9.11 hours
  4. D.7.11 hours
  5. E.8.11 hours
Show correct answer & explanation

Correct answer: D — 7.11 hours

Rates are 1/d and 1.25/d batches per hour. Combined rate 2.25/d has reciprocal d/2.25. Rounded to two decimal places, the answer is 7.11 hours.

QUESTION 2 OF 25

A, B, C have rates 2:3:5 and together finish in 16 days. B works alone for 16 days, then A andC finish. How many additional days are needed?

  1. A.18 days
  2. B.15 days
  3. C.14 days
  4. D.16 days
  5. E.17 days
Show correct answer & explanation

Correct answer: D — 16 days

B completes 3/10 of the task. A + C together contribute 7/10 of the all-team rate, so they complete the remaining 7/10 in the same 16 days.

QUESTION 3 OF 25

A andB can complete a job in 32 and 48 days. Both work 4 hours per day instead of their usual 8, without changing hourly productivity. What is completion time working together?

  1. A.36.4 days
  2. B.37.4 days
  3. C.40.4 days
  4. D.38.4 days
  5. E.39.4 days
Show correct answer & explanation

Correct answer: D — 38.4 days

Each daily rate halves. Their combined usual rate 5/(6d) becomes 5/(12d); reciprocal is 12d/5 days.

QUESTION 4 OF 25

A has completed 40% of a job in 16 days. B works twice as fast asA. How many further days would B alone need for the remaining work?

  1. A.13 days
  2. B.11 days
  3. C.12 days
  4. D.14 days
  5. E.10 days
Show correct answer & explanation

Correct answer: C — 12 days

A's rate is 0.40/d, so B's is 0.80/d. Remaining 0.60 work needs 0.60/(0.80/d)=0.75d days.

QUESTION 5 OF 25

A contractor's team has capacity 1600 units/day. It must deliver 40000 units in 20 days. What percentage increase in daily capacity is required?

  1. A.26%
  2. B.23%
  3. C.25%
  4. D.24%
  5. E.27%
Show correct answer & explanation

Correct answer: C — 25%

Required rate=(2500d)/20=125d units/day, compared with 100d. The increase 25d on 100d is 25%.

QUESTION 6 OF 25

A completes a task in 36 days and B in 54. They work together for 9 days, then B leaves. How many additional days does A need?

  1. A.20 days
  2. B.22 days
  3. C.21 days
  4. D.23 days
  5. E.19 days
Show correct answer & explanation

Correct answer: C — 21 days

Combined first-phase work is(d/2)(1/(2d)+1/(3d))=5/12. The remaining 7/12 takes A 2d×7/12=7d/6 days.

QUESTION 7 OF 25

A and B together finish a job in 18 days. A alone needs 54 days. B is paid ₹4200 when wages follow work contribution over equal hours. How much does A receive?

  1. A.2100
  2. B.2102
  3. C.2101
  4. D.2098
  5. E.2099
Show correct answer & explanation

Correct answer: A — 2100

B's rate is 1/d−1/(3d)=2/(3d), twice A's. Therefore A's contribution and wage are half B's.

QUESTION 8 OF 25

18 workers are to complete a job in 20 days. After 5 days, half as many additional workers join. At unchanged productivity, how many further days are needed?

  1. A.8 days
  2. B.12 days
  3. C.9 days
  4. D.11 days
  5. E.10 days
Show correct answer & explanation

Correct answer: E — 10 days

Five days complete one-quarter of work. Remaining work is 15d worker-days; new workforce 1.5d completes it in 10 days.

QUESTION 9 OF 25

A makes 180 units in 5 hours. B is 20% slower in units per hour. They both work for 10 hours. What total output results?

  1. A.649
  2. B.650
  3. C.648
  4. D.647
  5. E.646
Show correct answer & explanation

Correct answer: C — 648

A's rate is 2d units/hour; B's is 1.6d. Together at 3.6d for 10 hours they produce 36d units.

QUESTION 10 OF 25

A finishes a job in 36 days and B in 72. For the first 18 days only B works; then A joins. How many days does the final combined phase require?

  1. A.16 days
  2. B.17 days
  3. C.19 days
  4. D.20 days
  5. E.18 days
Show correct answer & explanation

Correct answer: E — 18 days

B first completes 1/4. Their combined daily rate is 3/(4d), so the remaining 3/4 takes d days.

QUESTION 11 OF 25

A machine makes a batch in 18 hours. A second machine is 25% more efficient. Both operate together. What is their combined completion time?

  1. A.7 hours
  2. B.9 hours
  3. C.8 hours
  4. D.6 hours
  5. E.10 hours
Show correct answer & explanation

Correct answer: C — 8 hours

Rates are 1/d and 1.25/d batches per hour. Combined rate 2.25/d has reciprocal d/2.25.

QUESTION 12 OF 25

A, B, C have rates 2:3:5 and together finish in 18 days. B works alone for 18 days, then A andC finish. How many additional days are needed?

  1. A.18 days
  2. B.19 days
  3. C.17 days
  4. D.20 days
  5. E.16 days
Show correct answer & explanation

Correct answer: A — 18 days

B completes 3/10 of the task. A + C together contribute 7/10 of the all-team rate, so they complete the remaining 7/10 in the same 18 days.

QUESTION 13 OF 25

A andB can complete a job in 36 and 54 days. Both work 4 hours per day instead of their usual 8, without changing hourly productivity. What is completion time working together?

  1. A.41.2 days
  2. B.42.2 days
  3. C.45.2 days
  4. D.44.2 days
  5. E.43.2 days
Show correct answer & explanation

Correct answer: E — 43.2 days

Each daily rate halves. Their combined usual rate 5/(6d) becomes 5/(12d); reciprocal is 12d/5 days.

QUESTION 14 OF 25

A has completed 40% of a job in 18 days. B works twice as fast asA. How many further days would B alone need for the remaining work?

  1. A.15.5 days
  2. B.14.5 days
  3. C.13.5 days
  4. D.12.5 days
  5. E.11.5 days
Show correct answer & explanation

Correct answer: C — 13.5 days

A's rate is 0.40/d, so B's is 0.80/d. Remaining 0.60 work needs 0.60/(0.80/d)=0.75d days.

QUESTION 15 OF 25

A contractor's team has capacity 1800 units/day. It must deliver 45000 units in 20 days. What percentage increase in daily capacity is required?

  1. A.24%
  2. B.25%
  3. C.26%
  4. D.23%
  5. E.27%
Show correct answer & explanation

Correct answer: B — 25%

Required rate=(2500d)/20=125d units/day, compared with 100d. The increase 25d on 100d is 25%.

QUESTION 16 OF 25

A completes a task in 40 days and B in 60. They work together for 10 days, then B leaves. How many additional days does A need? Round your answer to two decimal places.

  1. A.24.33 days
  2. B.25.33 days
  3. C.21.33 days
  4. D.22.33 days
  5. E.23.33 days
Show correct answer & explanation

Correct answer: E — 23.33 days

Combined first-phase work is(d/2)(1/(2d)+1/(3d))=5/12. The remaining 7/12 takes A 2d×7/12=7d/6 days. Rounded to two decimal places, the answer is 23.33 days.

QUESTION 17 OF 25

A and B together finish a job in 20 days. A alone needs 60 days. B is paid ₹4500 when wages follow work contribution over equal hours. How much does A receive?

  1. A.2250
  2. B.2251
  3. C.2249
  4. D.2252
  5. E.2248
Show correct answer & explanation

Correct answer: A — 2250

B's rate is 1/d−1/(3d)=2/(3d), twice A's. Therefore A's contribution and wage are half B's.

QUESTION 18 OF 25

20 workers are to complete a job in 20 days. After 5 days, half as many additional workers join. At unchanged productivity, how many further days are needed?

  1. A.12 days
  2. B.9 days
  3. C.8 days
  4. D.10 days
  5. E.11 days
Show correct answer & explanation

Correct answer: D — 10 days

Five days complete one-quarter of work. Remaining work is 15d worker-days; new workforce 1.5d completes it in 10 days.

QUESTION 19 OF 25

A makes 200 units in 5 hours. B is 20% slower in units per hour. They both work for 10 hours. What total output results?

  1. A.718
  2. B.722
  3. C.721
  4. D.719
  5. E.720
Show correct answer & explanation

Correct answer: E — 720

A's rate is 2d units/hour; B's is 1.6d. Together at 3.6d for 10 hours they produce 36d units.

QUESTION 20 OF 25

A finishes a job in 40 days and B in 80. For the first 20 days only B works; then A joins. How many days does the final combined phase require?

  1. A.22 days
  2. B.19 days
  3. C.18 days
  4. D.21 days
  5. E.20 days
Show correct answer & explanation

Correct answer: E — 20 days

B first completes 1/4. Their combined daily rate is 3/(4d), so the remaining 3/4 takes d days.

QUESTION 21 OF 25

A machine makes a batch in 20 hours. A second machine is 25% more efficient. Both operate together. What is their combined completion time? Round your answer to two decimal places.

  1. A.7.89 hours
  2. B.8.89 hours
  3. C.6.89 hours
  4. D.9.89 hours
  5. E.10.89 hours
Show correct answer & explanation

Correct answer: B — 8.89 hours

Rates are 1/d and 1.25/d batches per hour. Combined rate 2.25/d has reciprocal d/2.25. Rounded to two decimal places, the answer is 8.89 hours.

QUESTION 22 OF 25

A, B, C have rates 2:3:5 and together finish in 20 days. B works alone for 20 days, then A andC finish. How many additional days are needed?

  1. A.21 days
  2. B.19 days
  3. C.22 days
  4. D.18 days
  5. E.20 days
Show correct answer & explanation

Correct answer: E — 20 days

B completes 3/10 of the task. A + C together contribute 7/10 of the all-team rate, so they complete the remaining 7/10 in the same 20 days.

QUESTION 23 OF 25

A andB can complete a job in 40 and 60 days. Both work 4 hours per day instead of their usual 8, without changing hourly productivity. What is completion time working together?

  1. A.47 days
  2. B.49 days
  3. C.48 days
  4. D.50 days
  5. E.46 days
Show correct answer & explanation

Correct answer: C — 48 days

Each daily rate halves. Their combined usual rate 5/(6d) becomes 5/(12d); reciprocal is 12d/5 days.

QUESTION 24 OF 25

A has completed 40% of a job in 20 days. B works twice as fast asA. How many further days would B alone need for the remaining work?

  1. A.16 days
  2. B.15 days
  3. C.14 days
  4. D.13 days
  5. E.17 days
Show correct answer & explanation

Correct answer: B — 15 days

A's rate is 0.40/d, so B's is 0.80/d. Remaining 0.60 work needs 0.60/(0.80/d)=0.75d days.

QUESTION 25 OF 25

A contractor's team has capacity 2000 units/day. It must deliver 50000 units in 20 days. What percentage increase in daily capacity is required?

  1. A.25%
  2. B.27%
  3. C.26%
  4. D.23%
  5. E.24%
Show correct answer & explanation

Correct answer: A — 25%

Required rate=(2500d)/20=125d units/day, compared with 100d. The increase 25d on 100d is 25%.

Made for focused preparation.3 free test attempts · ₹19 permanently unlocks one exam, including all current and future topic practice, mocks and PYQs.