A can complete a job in 14 days and B in 21 days. Working together at constant rates, how many days do they need?

  1. A.7.4 days
  2. B.10.4 days
  3. C.6.4 days
  4. D.9.4 days
  5. E.8.4 days
Show correct answer & explanation

Correct answer: E — 8.4 days

Combined daily rate is 1/14+1/21=5/(42). Required duration is the reciprocal, 42/5 days.

QUESTION 2 OF 25

A completes a job in 14 days. After A works alone for 7 days, B completes the remainder in 14 days. How long would B alone take for the whole job?

  1. A.26 days
  2. B.28 days
  3. C.30 days
  4. D.27 days
  5. E.29 days
Show correct answer & explanation

Correct answer: B — 28 days

A completes half the job. B takes 14 days for the other half, so the full-job time at B's rate is twice that duration.

QUESTION 3 OF 25

7 workers finish a job in 12 days at 8 hours per day. How many days would 14 equally productive workers take at 6 hours per day?

  1. A.10 days
  2. B.7 days
  3. C.8 days
  4. D.9 days
  5. E.6 days
Show correct answer & explanation

Correct answer: C — 8 days

Total work is 7×12×8 worker-hours. Divide by (14×6) daily worker-hours to obtain 8 days.

QUESTION 4 OF 25

A is 50% more efficient than B. B takes 21 days alone. In how many days can A alone complete the same job?

  1. A.16 days
  2. B.12 days
  3. C.15 days
  4. D.13 days
  5. E.14 days
Show correct answer & explanation

Correct answer: E — 14 days

A's work rate is 1.5 times B's, so A's time is B's time divided by 1.5: 21/1.5=14.

QUESTION 5 OF 25

A and B have work rates in the ratio 2:3 and work equal hours. Their total wage is ₹5500, paid in proportion to output. What is A's wage in rupees?

  1. A.2200
  2. B.2199
  3. C.2201
  4. D.2198
  5. E.2202
Show correct answer & explanation

Correct answer: A — 2200

Equal hours make output ratio equal rate ratio, 2:3. A receives two-fifths of the total wage.

QUESTION 6 OF 25

A can finish a job in 21 days; B can finish it in 42 days. They work together for 7 days, then A leaves. How many additional days does B need?

  1. A.20 days
  2. B.23 days
  3. C.22 days
  4. D.21 days
  5. E.19 days
Show correct answer & explanation

Correct answer: D — 21 days

Together they complete 7 × (1/21+1/42)=1/2. B needs half of the whole-job time 42 to finish the remainder.

QUESTION 7 OF 25

A, B and C alone finish a job in 14, 21 and 42 days. How many days do they need together?

  1. A.6 days
  2. B.8 days
  3. C.9 days
  4. D.5 days
  5. E.7 days
Show correct answer & explanation

Correct answer: E — 7 days

Their rates sum to 1/(2d)+1/(3d)+1/(6d)=1/d where d=7. The total duration is therefore 7 days.

QUESTION 8 OF 25

A works twice as fast as B. Together they complete a task in 7 days. How many days would B alone need?

  1. A.19 days
  2. B.21 days
  3. C.22 days
  4. D.20 days
  5. E.23 days
Show correct answer & explanation

Correct answer: B — 21 days

If B's daily rate is b, A's is 2b and together the rate is 3b=1/7. Thus B's whole-job time is 3 × 7.

QUESTION 9 OF 25

A team planned to complete 700 units in 10 days. After producing half the units in 6 days, it must finish on schedule. What daily output is required over the remaining days?

  1. A.85.5 units/day
  2. B.89.5 units/day
  3. C.88.5 units/day
  4. D.86.5 units/day
  5. E.87.5 units/day
Show correct answer & explanation

Correct answer: E — 87.5 units/day

Remaining work is 350 units and remaining time is 4 days. Required daily output is remaining work divided by 4.

QUESTION 10 OF 25

A completes a job in 14 days and B in 28. They alternate whole days, A first, stopping immediately when the job finishes. How many elapsed days are required?

  1. A.19.5 days
  2. B.20.5 days
  3. C.17.5 days
  4. D.18.5 days
  5. E.16.5 days
Show correct answer & explanation

Correct answer: D — 18.5 days

Use 28 work units: A does 2 units/day, B 1. Every two-day cycle finishes 3 units. After full cycles, use A's next day and, if necessary, a fractional final day.

QUESTION 11 OF 25

A can complete a job in 16 days and B in 24 days. Working together at constant rates, how many days do they need?

  1. A.9.6 days
  2. B.7.6 days
  3. C.10.6 days
  4. D.8.6 days
  5. E.11.6 days
Show correct answer & explanation

Correct answer: A — 9.6 days

Combined daily rate is 1/16+1/24=5/(48). Required duration is the reciprocal, 48/5 days.

QUESTION 12 OF 25

A completes a job in 16 days. After A works alone for 8 days, B completes the remainder in 16 days. How long would B alone take for the whole job?

  1. A.33 days
  2. B.31 days
  3. C.34 days
  4. D.30 days
  5. E.32 days
Show correct answer & explanation

Correct answer: E — 32 days

A completes half the job. B takes 16 days for the other half, so the full-job time at B's rate is twice that duration.

QUESTION 13 OF 25

8 workers finish a job in 12 days at 8 hours per day. How many days would 16 equally productive workers take at 6 hours per day?

  1. A.8 days
  2. B.6 days
  3. C.10 days
  4. D.7 days
  5. E.9 days
Show correct answer & explanation

Correct answer: A — 8 days

Total work is 8×12×8 worker-hours. Divide by (16×6) daily worker-hours to obtain 8 days.

QUESTION 14 OF 25

A is 50% more efficient than B. B takes 24 days alone. In how many days can A alone complete the same job?

  1. A.17 days
  2. B.14 days
  3. C.18 days
  4. D.15 days
  5. E.16 days
Show correct answer & explanation

Correct answer: E — 16 days

A's work rate is 1.5 times B's, so A's time is B's time divided by 1.5: 24/1.5=16.

QUESTION 15 OF 25

A and B have work rates in the ratio 2:3 and work equal hours. Their total wage is ₹6000, paid in proportion to output. What is A's wage in rupees?

  1. A.2399
  2. B.2401
  3. C.2400
  4. D.2402
  5. E.2398
Show correct answer & explanation

Correct answer: C — 2400

Equal hours make output ratio equal rate ratio, 2:3. A receives two-fifths of the total wage.

QUESTION 16 OF 25

A can finish a job in 24 days; B can finish it in 48 days. They work together for 8 days, then A leaves. How many additional days does B need?

  1. A.22 days
  2. B.23 days
  3. C.24 days
  4. D.25 days
  5. E.26 days
Show correct answer & explanation

Correct answer: C — 24 days

Together they complete 8 × (1/24+1/48)=1/2. B needs half of the whole-job time 48 to finish the remainder.

QUESTION 17 OF 25

A, B and C alone finish a job in 16, 24 and 48 days. How many days do they need together?

  1. A.9 days
  2. B.7 days
  3. C.8 days
  4. D.6 days
  5. E.10 days
Show correct answer & explanation

Correct answer: C — 8 days

Their rates sum to 1/(2d)+1/(3d)+1/(6d)=1/d where d=8. The total duration is therefore 8 days.

QUESTION 18 OF 25

A works twice as fast as B. Together they complete a task in 8 days. How many days would B alone need?

  1. A.23 days
  2. B.25 days
  3. C.24 days
  4. D.22 days
  5. E.26 days
Show correct answer & explanation

Correct answer: C — 24 days

If B's daily rate is b, A's is 2b and together the rate is 3b=1/8. Thus B's whole-job time is 3 × 8.

QUESTION 19 OF 25

A team planned to complete 800 units in 10 days. After producing half the units in 6 days, it must finish on schedule. What daily output is required over the remaining days?

  1. A.99 units/day
  2. B.102 units/day
  3. C.98 units/day
  4. D.100 units/day
  5. E.101 units/day
Show correct answer & explanation

Correct answer: D — 100 units/day

Remaining work is 400 units and remaining time is 4 days. Required daily output is remaining work divided by 4.

QUESTION 20 OF 25

A completes a job in 16 days and B in 32. They alternate whole days, A first, stopping immediately when the job finishes. How many elapsed days are required?

  1. A.23 days
  2. B.21 days
  3. C.22 days
  4. D.19 days
  5. E.20 days
Show correct answer & explanation

Correct answer: B — 21 days

Use 32 work units: A does 2 units/day, B 1. Every two-day cycle finishes 3 units. After full cycles, use A's next day and, if necessary, a fractional final day.

QUESTION 21 OF 25

A can complete a job in 18 days and B in 27 days. Working together at constant rates, how many days do they need?

  1. A.12.8 days
  2. B.10.8 days
  3. C.11.8 days
  4. D.8.8 days
  5. E.9.8 days
Show correct answer & explanation

Correct answer: B — 10.8 days

Combined daily rate is 1/18+1/27=5/(54). Required duration is the reciprocal, 54/5 days.

QUESTION 22 OF 25

A completes a job in 18 days. After A works alone for 9 days, B completes the remainder in 18 days. How long would B alone take for the whole job?

  1. A.38 days
  2. B.34 days
  3. C.36 days
  4. D.37 days
  5. E.35 days
Show correct answer & explanation

Correct answer: C — 36 days

A completes half the job. B takes 18 days for the other half, so the full-job time at B's rate is twice that duration.

QUESTION 23 OF 25

9 workers finish a job in 12 days at 8 hours per day. How many days would 18 equally productive workers take at 6 hours per day?

  1. A.7 days
  2. B.10 days
  3. C.8 days
  4. D.9 days
  5. E.6 days
Show correct answer & explanation

Correct answer: C — 8 days

Total work is 9×12×8 worker-hours. Divide by (18×6) daily worker-hours to obtain 8 days.

QUESTION 24 OF 25

A is 50% more efficient than B. B takes 27 days alone. In how many days can A alone complete the same job?

  1. A.18 days
  2. B.20 days
  3. C.16 days
  4. D.17 days
  5. E.19 days
Show correct answer & explanation

Correct answer: A — 18 days

A's work rate is 1.5 times B's, so A's time is B's time divided by 1.5: 27/1.5=18.

QUESTION 25 OF 25

A and B have work rates in the ratio 2:3 and work equal hours. Their total wage is ₹6500, paid in proportion to output. What is A's wage in rupees?

  1. A.2601
  2. B.2602
  3. C.2600
  4. D.2599
  5. E.2598
Show correct answer & explanation

Correct answer: C — 2600

Equal hours make output ratio equal rate ratio, 2:3. A receives two-fifths of the total wage.

Made for focused preparation.3 free test attempts · ₹19 permanently unlocks one exam, including all current and future topic practice, mocks and PYQs.