QUESTION 1 OF 25

A can finish a job in 27 days; B can finish it in 54 days. They work together for 9 days, then A leaves. How many additional days does B need?

  1. A.26 days
  2. B.28 days
  3. C.27 days
  4. D.29 days
  5. E.25 days
Show correct answer & explanation

Correct answer: C — 27 days

Together they complete 9 × (1/27+1/54)=1/2. B needs half of the whole-job time 54 to finish the remainder.

QUESTION 2 OF 25

A, B and C alone finish a job in 18, 27 and 54 days. How many days do they need together?

  1. A.8 days
  2. B.9 days
  3. C.7 days
  4. D.10 days
  5. E.11 days
Show correct answer & explanation

Correct answer: B — 9 days

Their rates sum to 1/(2d)+1/(3d)+1/(6d)=1/d where d=9. The total duration is therefore 9 days.

QUESTION 3 OF 25

A works twice as fast as B. Together they complete a task in 9 days. How many days would B alone need?

  1. A.26 days
  2. B.25 days
  3. C.29 days
  4. D.28 days
  5. E.27 days
Show correct answer & explanation

Correct answer: E — 27 days

If B's daily rate is b, A's is 2b and together the rate is 3b=1/9. Thus B's whole-job time is 3 × 9.

QUESTION 4 OF 25

A team planned to complete 900 units in 10 days. After producing half the units in 6 days, it must finish on schedule. What daily output is required over the remaining days?

  1. A.112.5 units/day
  2. B.113.5 units/day
  3. C.110.5 units/day
  4. D.111.5 units/day
  5. E.114.5 units/day
Show correct answer & explanation

Correct answer: A — 112.5 units/day

Remaining work is 450 units and remaining time is 4 days. Required daily output is remaining work divided by 4.

QUESTION 5 OF 25

A completes a job in 18 days and B in 36. They alternate whole days, A first, stopping immediately when the job finishes. How many elapsed days are required?

  1. A.22 days
  2. B.23 days
  3. C.26 days
  4. D.24 days
  5. E.25 days
Show correct answer & explanation

Correct answer: D — 24 days

Use 36 work units: A does 2 units/day, B 1. Every two-day cycle finishes 3 units. After full cycles, use A's next day and, if necessary, a fractional final day.

QUESTION 6 OF 25

A can complete a job in 20 days and B in 30 days. Working together at constant rates, how many days do they need?

  1. A.14 days
  2. B.10 days
  3. C.13 days
  4. D.12 days
  5. E.11 days
Show correct answer & explanation

Correct answer: D — 12 days

Combined daily rate is 1/20+1/30=5/(60). Required duration is the reciprocal, 60/5 days.

QUESTION 7 OF 25

A completes a job in 20 days. After A works alone for 10 days, B completes the remainder in 20 days. How long would B alone take for the whole job?

  1. A.38 days
  2. B.41 days
  3. C.42 days
  4. D.39 days
  5. E.40 days
Show correct answer & explanation

Correct answer: E — 40 days

A completes half the job. B takes 20 days for the other half, so the full-job time at B's rate is twice that duration.

QUESTION 8 OF 25

10 workers finish a job in 12 days at 8 hours per day. How many days would 20 equally productive workers take at 6 hours per day?

  1. A.6 days
  2. B.7 days
  3. C.8 days
  4. D.10 days
  5. E.9 days
Show correct answer & explanation

Correct answer: C — 8 days

Total work is 10×12×8 worker-hours. Divide by (20×6) daily worker-hours to obtain 8 days.

QUESTION 9 OF 25

A is 50% more efficient than B. B takes 30 days alone. In how many days can A alone complete the same job?

  1. A.22 days
  2. B.18 days
  3. C.20 days
  4. D.19 days
  5. E.21 days
Show correct answer & explanation

Correct answer: C — 20 days

A's work rate is 1.5 times B's, so A's time is B's time divided by 1.5: 30/1.5=20.

QUESTION 10 OF 25

A and B have work rates in the ratio 2:3 and work equal hours. Their total wage is ₹7000, paid in proportion to output. What is A's wage in rupees?

  1. A.2800
  2. B.2799
  3. C.2801
  4. D.2798
  5. E.2802
Show correct answer & explanation

Correct answer: A — 2800

Equal hours make output ratio equal rate ratio, 2:3. A receives two-fifths of the total wage.

QUESTION 11 OF 25

A can finish a job in 30 days; B can finish it in 60 days. They work together for 10 days, then A leaves. How many additional days does B need?

  1. A.32 days
  2. B.28 days
  3. C.30 days
  4. D.31 days
  5. E.29 days
Show correct answer & explanation

Correct answer: C — 30 days

Together they complete 10 × (1/30+1/60)=1/2. B needs half of the whole-job time 60 to finish the remainder.

QUESTION 12 OF 25

A, B and C alone finish a job in 20, 30 and 60 days. How many days do they need together?

  1. A.11 days
  2. B.9 days
  3. C.12 days
  4. D.8 days
  5. E.10 days
Show correct answer & explanation

Correct answer: E — 10 days

Their rates sum to 1/(2d)+1/(3d)+1/(6d)=1/d where d=10. The total duration is therefore 10 days.

QUESTION 13 OF 25

A works twice as fast as B. Together they complete a task in 10 days. How many days would B alone need?

  1. A.30 days
  2. B.32 days
  3. C.31 days
  4. D.29 days
  5. E.28 days
Show correct answer & explanation

Correct answer: A — 30 days

If B's daily rate is b, A's is 2b and together the rate is 3b=1/10. Thus B's whole-job time is 3 × 10.

QUESTION 14 OF 25

A team planned to complete 1000 units in 10 days. After producing half the units in 6 days, it must finish on schedule. What daily output is required over the remaining days?

  1. A.125 units/day
  2. B.123 units/day
  3. C.126 units/day
  4. D.124 units/day
  5. E.127 units/day
Show correct answer & explanation

Correct answer: A — 125 units/day

Remaining work is 500 units and remaining time is 4 days. Required daily output is remaining work divided by 4.

QUESTION 15 OF 25

A completes a job in 20 days and B in 40. They alternate whole days, A first, stopping immediately when the job finishes. How many elapsed days are required?

  1. A.25.5 days
  2. B.26.5 days
  3. C.27.5 days
  4. D.24.5 days
  5. E.28.5 days
Show correct answer & explanation

Correct answer: B — 26.5 days

Use 40 work units: A does 2 units/day, B 1. Every two-day cycle finishes 3 units. After full cycles, use A's next day and, if necessary, a fractional final day.

QUESTION 16 OF 25

A can complete a job in 22 days and B in 33 days. Working together at constant rates, how many days do they need?

  1. A.13.2 days
  2. B.14.2 days
  3. C.15.2 days
  4. D.12.2 days
  5. E.11.2 days
Show correct answer & explanation

Correct answer: A — 13.2 days

Combined daily rate is 1/22+1/33=5/(66). Required duration is the reciprocal, 66/5 days.

QUESTION 17 OF 25

A completes a job in 22 days. After A works alone for 11 days, B completes the remainder in 22 days. How long would B alone take for the whole job?

  1. A.43 days
  2. B.45 days
  3. C.46 days
  4. D.42 days
  5. E.44 days
Show correct answer & explanation

Correct answer: E — 44 days

A completes half the job. B takes 22 days for the other half, so the full-job time at B's rate is twice that duration.

QUESTION 18 OF 25

11 workers finish a job in 12 days at 8 hours per day. How many days would 22 equally productive workers take at 6 hours per day?

  1. A.8 days
  2. B.9 days
  3. C.7 days
  4. D.6 days
  5. E.10 days
Show correct answer & explanation

Correct answer: A — 8 days

Total work is 11×12×8 worker-hours. Divide by (22×6) daily worker-hours to obtain 8 days.

QUESTION 19 OF 25

A is 50% more efficient than B. B takes 33 days alone. In how many days can A alone complete the same job?

  1. A.21 days
  2. B.23 days
  3. C.20 days
  4. D.24 days
  5. E.22 days
Show correct answer & explanation

Correct answer: E — 22 days

A's work rate is 1.5 times B's, so A's time is B's time divided by 1.5: 33/1.5=22.

QUESTION 20 OF 25

A and B have work rates in the ratio 2:3 and work equal hours. Their total wage is ₹7500, paid in proportion to output. What is A's wage in rupees?

  1. A.2998
  2. B.3002
  3. C.3000
  4. D.3001
  5. E.2999
Show correct answer & explanation

Correct answer: C — 3000

Equal hours make output ratio equal rate ratio, 2:3. A receives two-fifths of the total wage.

QUESTION 21 OF 25

A can finish a job in 33 days; B can finish it in 66 days. They work together for 11 days, then A leaves. How many additional days does B need?

  1. A.32 days
  2. B.33 days
  3. C.31 days
  4. D.35 days
  5. E.34 days
Show correct answer & explanation

Correct answer: B — 33 days

Together they complete 11 × (1/33+1/66)=1/2. B needs half of the whole-job time 66 to finish the remainder.

QUESTION 22 OF 25

A, B and C alone finish a job in 22, 33 and 66 days. How many days do they need together?

  1. A.9 days
  2. B.13 days
  3. C.11 days
  4. D.10 days
  5. E.12 days
Show correct answer & explanation

Correct answer: C — 11 days

Their rates sum to 1/(2d)+1/(3d)+1/(6d)=1/d where d=11. The total duration is therefore 11 days.

QUESTION 23 OF 25

A works twice as fast as B. Together they complete a task in 11 days. How many days would B alone need?

  1. A.33 days
  2. B.31 days
  3. C.32 days
  4. D.35 days
  5. E.34 days
Show correct answer & explanation

Correct answer: A — 33 days

If B's daily rate is b, A's is 2b and together the rate is 3b=1/11. Thus B's whole-job time is 3 × 11.

QUESTION 24 OF 25

A team planned to complete 1100 units in 10 days. After producing half the units in 6 days, it must finish on schedule. What daily output is required over the remaining days?

  1. A.139.5 units/day
  2. B.138.5 units/day
  3. C.135.5 units/day
  4. D.136.5 units/day
  5. E.137.5 units/day
Show correct answer & explanation

Correct answer: E — 137.5 units/day

Remaining work is 550 units and remaining time is 4 days. Required daily output is remaining work divided by 4.

QUESTION 25 OF 25

A completes a job in 22 days and B in 44. They alternate whole days, A first, stopping immediately when the job finishes. How many elapsed days are required?

  1. A.29 days
  2. B.30 days
  3. C.28 days
  4. D.31 days
  5. E.27 days
Show correct answer & explanation

Correct answer: A — 29 days

Use 44 work units: A does 2 units/day, B 1. Every two-day cycle finishes 3 units. After full cycles, use A's next day and, if necessary, a fractional final day.

Made for focused preparation.3 free test attempts · ₹19 permanently unlocks one exam, including all current and future topic practice, mocks and PYQs.